Signing date
When the documents were signed. Check separately whether a deposit, drawing approval or start condition is linked to it.
SII / SCHEDULE FOLLOW-UP
Find out which work is delayed, how much time it affects and what happens next. Compare the original dates, the delay notice and the revised plan. “A little longer” does not tell you when the remaining work will be done.
Still reviewing a contract? Use the same questions to clarify the start conditions, completion scope, extensions and notices.
Illustrative record · not a real case
Keep the original schedule and add a dated revision. Do not overwrite the old dates.
Separate what is known from what still needs an answer. These steps organize the documents; they do not determine fault or compensation.
Compare the original schedule with completed work and site records. Note what should have been finished, by when, and its current status. The number of people on site is not a progress record.
Request the event, its timing, the affected work, the estimated delay and how that estimate was reached. If details are unknown, record who will provide them and when the next update is due.
Ask for a dated revision showing the remaining sequence, stage checks, completion and handover. A new final date alone does not show how the work will get there.
Compare each payment condition with the work and documents actually completed. Keep proposed extra costs, extensions and payment changes separate. Do not use this checklist alone to decide to withhold or deduct payment.
Keep the quote, contract, old and new schedules, site photos, additions and deductions, delay notices and payment records together. Mark unresolved points as awaiting confirmation.
Use these labels to check the records. Your actual start and completion conditions depend on the project agreement.
When the documents were signed. Check separately whether a deposit, drawing approval or start condition is linked to it.
When work is intended to begin. Check drawings, selections, permissions, site access and any agreed payment prerequisites.
Record what work started and when. Then check whether that event meets the agreed condition for starting the clock.
The original target for the agreed scope. Retain it when scope changes and record why a revision is proposed.
Check the agreed completion requirements, not simply the last day someone worked on site.
Record the acceptance outcome, defect follow-up and document delivery. Clarify which requirements must be met before acceptance is complete.
Open a question for wording you can use and the record to ask for. Treat missing information as a request for clarification, not an assumed agreement.
Does the duration use calendar days, working days or days actually worked on site? Please define the calculation and the treatment of weekends, holidays, building restrictions and stoppages.
Keep this recordThe calculation method, excluded dates and stop/restart records. A total number of days is not enough to explain the count.
Which drawings, selections, permissions, access arrangements and payments must be completed before the duration starts? Please name the responsible parties, planned dates and how the actual start will be confirmed.
Keep this recordPrerequisites, each party’s outstanding tasks and the start confirmation. Do not substitute the signing date for the start date.
How are material waiting periods, building restrictions and other periods when work cannot proceed counted? If an extension is proposed, please identify the agreed basis, affected work, extra days and confirmation process.
Keep this recordThe specific event and period, the relevant agreement, affected tasks and both parties’ replies.
Does completion include cleaning, tests, defect correction, equipment and document delivery? Please distinguish work completion, initial and follow-up inspections, handover and the warranty start, with their conditions and dates.
Keep this recordCompletion requirements, inspection and handover lists, and the relationship between dates. Leaving the site is not the same as finishing every obligation.
For each addition, deduction or change, will the work sequence or duration change? Please list estimated added or reduced days separately from costs, with revised milestone and completion dates for both parties to check.
Keep this recordOne change reference linking scope, amount, time impact, schedule version and confirmation records.
What agreed provisions apply to material shortages, staffing, weather or an event described as force majeure? Please set out notices, supporting records, alternatives and time and cost effects, rather than simply citing site conditions.
Keep this recordThe explanation, effects and missing information. Whether an event qualifies as force majeure or creates liability requires appropriate project-specific professional advice.
When a delay is expected, who notifies whom, when and by which channel? When will the revised schedule be provided? If the completion date is uncertain, please identify what is unresolved and when the next update will be given.
Keep this recordAgreed channels, recipients, timing, acknowledgements, outstanding replies and schedule revisions—not only verbal promises.
What completed work, checks or documents correspond to each stage payment? If work is delayed, please identify what is unfinished and which payment, recovery or follow-up arrangements need separate confirmation under the existing agreement.
Keep this recordA comparison of stage outcomes, checks and payment conditions. Seek qualified legal advice on liability, compensation or termination.
These examples do not establish that a clause is invalid or that someone has breached a contract. They show what information to ask for.
Starting from which event, and using which kind of days? Establish the starting point and counting method before comparing progress.
When will you notify us, with what explanation and revised plan? How do both parties confirm the change, and what happens if they disagree?
Which event affected which work, for how long? Please explain each event against the relevant agreement instead of grouping every cause together.
Was the time impact also confirmed? Record added or reduced days, affected tasks and the proposed new dates.
What work or documents do the original payment conditions refer to, and are they complete? Record any proposed adjustment separately.
What will be finished next, when, and who will update us? If no workable plan is provided, retain the correspondence and seek appropriate professional help.
Add the project name, original schedule version and known facts before sending. This asks for information; it does not accept an extension, payment change or allocation of responsibility.
STANDARD INTEGRITY INSTITUTE
READ → COMPARE → DISCUSS
SII reviews documents for Transparency, Consistency, Reasonableness and Executability to identify information worth clarifying. It does not rate contractors or determine breach, compensation, force majeure or actual site progress.
First establish what each date means. Then check duration calculations, prerequisites, completion scope, extensions, notices and stage acceptance. Dates alone do not explain how changes will be handled.
This checklist does not prescribe a universal choice. Agree the method explicitly, including weekends, holidays, building restrictions and stoppages, so the same number of days does not produce different expected dates.
The word “shortage” alone does not settle that question. Check the agreement and ask for affected tasks, notices, records, alternatives and estimated days. Disputed extension rights or liability require project-specific legal advice.
Do not infer agreement on time from agreement on a price. Record the work sequence and time effects separately, check revised milestone, completion and acceptance dates, and retain both parties’ responses.
This page does not recommend withholding, deducting or making payment. Compare the contract’s payment conditions with completed work, notices and dispute provisions. If the parties disagree, seek suitable legal advice with the documents and correspondence.
No. SII identifies missing, ambiguous or unconfirmed information in documents. It does not issue legal liability, compensation or engineering conclusions. Those questions need appropriate professionals to consider the actual documents and facts.
General document checks and inquiry prompts only—not legal advice, engineering assessment, site supervision or a decision on responsibility. Illustrations are not real cases or universal project durations or notice periods.